West Virginia Federal Court Refuses to Force Non-Signatory to Participate in Arbitration

Mountain Valley Pipeline LLC (MVP) contracted with U.S. Trinity Energy Services LLC for the construction and installation of the Mountain Valley Pipeline across property in Greenbrier County, West Virginia. Trinity subcontracted with M.T. Bores LLC to furnish equipment to excavate a tunnel in connection with the installation of the pipeline. But before the installation was completed, MVP terminated the project.

M.T. Bores claimed that it was not paid in full for the excavation equipment and thereafter placed a mechanic’s lien against the property for the balance due. M.T. Bores then instituted an action in the Greenbrier County Circuit Court seeking enforcement of the mechanic’s lien against MVP’s real property. The case was removed to the U.S. District Court for the Southern District of West Virginia, and Trinity thereafter moved to compel arbitration under the arbitration clause in the subcontract between M.T. Bores and Trinity. M.T. Bores did not dispute that it was required to arbitrate its claims but rather sought to compel MVP to participate in the arbitration.

Although recognizing that MVP was not a party to the subcontract, M.T. Bores sought to compel MVP’s participation based on the doctrine of equitable estoppel and third-party beneficiary theory. M.T. Bores argued that MVP should be estopped from refusing to arbitrate because it directly benefitted from the subcontract since the equipment contributed to MVP’s pipeline. The district court declined to apply the doctrine of equitable estoppel where MVP had not asserted any claim against M.T. Bores arising from the subcontract but rather was only defending claims brought against it by M.T. Bores. The district court similarly rejected M.T. Bores’ argument that MVP was a third-party beneficiary of the subcontract insofar as it was the owner of the property that was the site of M.T. Bores’ performance under the subcontract, finding that there was no evidence that the subcontract was created for MVP’s sole benefit. The district court noted that “[a] project owner will doubtless receive incidental benefits from its contractor's subcontracts; but those benefits alone will not render the owner a third-party beneficiary.”

M.T. Bores also argued that MVP should be compelled to arbitrate in the interest of judicial economy since the claims against MVP and Trinity were inextricably intertwined. Although the district court agreed that M.T. Bores’ claims against MVP and Trinity involved some overlapping legal and factual issues, the court found the claims were not so “inextricably intertwined” to justify requiring MVP to participate in an arbitration absent its consent.

The district court similarly found no merit to M.T. Bores’ argument that MVP was an essential party to the arbitration since Trinity’s payment obligations to M.T. Bores under the subcontract were linked to, and may have been contingent on, MVP’s payment to Trinity.

Even so, the district court noted that an express provision in the subcontract deprived M.T. Bores of the ability to compel MVP to arbitrate absent Trinity’s consent. The district court accordingly denied M.T. Bores’ motion to compel MVP to participate in the arbitration between Trinity and M.T. Bores.

M.T. Bores, LLC v. Mountain Valley Pipeline, LLC, No. 5:20-cv-00602 (S.D. W. Va. Aug. 2, 2021).

Related Practices
Reinsurance
©2026 Carlton Fields, P.A. Carlton Fields practices law in California through Carlton Fields, LLP. Carlton Fields publications should not be construed as legal advice on any specific facts or circumstances. The contents are intended for general information and educational purposes only, and should not be relied on as if it were advice about a particular fact situation. The distribution of this publication is not intended to create, and receipt of it does not constitute, an attorney-client relationship with Carlton Fields. This publication may not be quoted or referred to in any other publication or proceeding without the prior written consent of the firm, to be given or withheld at our discretion. To request reprint permission for any of our publications, please use our Contact Us form via the link below. The views set forth herein are the personal views of the author and do not necessarily reflect those of the firm. This site may contain hypertext links to information created and maintained by other entities. Carlton Fields does not control or guarantee the accuracy or completeness of this outside information, nor is the inclusion of a link to be intended as an endorsement of those outside sites.

Disclaimer

The information on this website is presented as a service for our clients and Internet users and is not intended to be legal advice, nor should you consider it as such. Although we welcome your inquiries, please keep in mind that merely contacting us will not establish an attorney-client relationship between us. Consequently, you should not convey any confidential information to us until a formal attorney-client relationship has been established. Please remember that electronic correspondence on the internet is not secure and that you should not include sensitive or confidential information in messages. With that in mind, we look forward to hearing from you.